Is a Contractor Entitled to an Extension of Time and Costs for Concurrent Delays?

Concurrent Delays in Construction: Is a Contractor Entitled to an Extension of Time and Prolongation Costs? Introduction Concurrent delay is one of the most contentious subjects in construction claims. It arises where two or more delay events, attributable to different parties, overlap and contribute to delayed project completion. A typical example is where the Employer […]

November 16, 20264 min read
Is a Contractor Entitled to an Extension of Time and Costs for Concurrent Delays?

Concurrent Delays in Construction: Is a Contractor Entitled to an Extension of Time and Prolongation Costs?

Introduction

Concurrent delay is one of the most contentious subjects in construction claims. It arises where two or more delay events, attributable to different parties, overlap and contribute to delayed project completion.

A typical example is where the Employer delays access to a construction site while the Contractor simultaneously experiences delays in mobilising labour, equipment or materials. Both events may affect the critical path and contribute to late completion.

The key question is whether the Contractor is entitled to an Extension of Time (EOT), prolongation costs or both.

Understanding Concurrent Delay

Concurrent delay generally occurs where an Employer-risk event and a Contractor-risk event independently affect the critical path during an overlapping period.

However, the mere occurrence of two delay events at the same time does not establish concurrency. For example, an Employer’s late approval of a critical drawing and the Contractor’s late procurement of materials may occur simultaneously, but if procurement does not affect the critical path, the events are not necessarily concurrent delays to completion.

The assessment must therefore establish whether each event independently contributed to delaying project completion, rather than simply comparing the dates on which the events occurred.

Is the Contractor Entitled to an Extension of Time?

The Society of Construction Law (SCL) Delay and Disruption Protocol generally supports granting an EOT where an Employer-risk delay and a Contractor-risk delay occur concurrently. The Contractor’s own delay should not automatically defeat an otherwise valid entitlement arising from the Employer’s delay.

For example, assume the Contractor experiences a 30-day delay in completing foundation works, while the Employer subsequently causes a 20-day delay by failing to provide access to the next work area. If both events affect the critical path during the same 20-day period, the Contractor may be entitled to an EOT for the Employer-risk event.

However, this is not an absolute rule. The contractual provisions, governing law and allocation of delay risks must be considered.

In North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744, the English Court of Appeal upheld an express contractual provision allocating concurrent delay risk to the Contractor. This demonstrates that the parties’ contractual agreement can significantly influence entitlement.

Is the Contractor Also Entitled to Prolongation Costs?

This is where the distinction between time and financial entitlement becomes important.

An EOT protects the Contractor against the consequences of delayed completion, particularly liquidated damages. Prolongation costs compensate for additional expenditure arising from a compensable delay event, subject to the contract.

Under Core Principle 14 of the SCL Protocol, where Employer Delay to Completion and Contractor Delay to Completion occur concurrently, the Contractor should only recover prolongation compensation to the extent that additional costs attributable to the Employer’s delay can be separated from those arising from its own delay.

Consider a Contractor experiencing a 30-day procurement delay, while the Employer causes a concurrent 20-day delay through late approval of drawings. Although the Contractor may qualify for a 20-day EOT, it does not automatically follow that the Employer must pay all site management, security, equipment and accommodation costs incurred during those days.

If the Contractor would have incurred those costs anyway because of its own procurement delay, establishing the Employer’s financial liability becomes more difficult.

Nevertheless, concurrent delay does not automatically extinguish every financial entitlement. The Contractor may still recover identifiable additional expenditure directly attributable to the Employer’s actions, provided the contract allows such recovery.

The Importance of Delay Analysis and Records

A successful concurrent delay claim requires more than demonstrating overlapping delay periods. The Contractor must establish the critical path impact of each event and demonstrate its effect on completion.

For financial claims, contemporaneous records are equally important. Payroll records, equipment logs, plant hire invoices, site establishment costs and correspondence can help demonstrate additional expenditure attributable to the Employer-risk event.

Without credible delay analysis and supporting records, a Contractor may establish entitlement to time but fail to substantiate its financial claim.

Conclusion

A Contractor may be entitled to an EOT for concurrent delays without necessarily being entitled to prolongation costs for the same period.

The distinction is that an EOT addresses the contractual consequences of delayed completion, whereas prolongation costs require proof of additional compensable expenditure and an appropriate contractual basis for recovery.

Ultimately, concurrent delay should not be approached as a simple exercise of counting overlapping days. It requires an examination of causation, critical path impact, contractual risk allocation and actual financial consequences.

Proving that the Employer contributed to the delay is not necessarily the same as proving that the Employer is liable for the costs incurred during that delay.

Share

Construction Claims

Have a project issue
that needs to be understood?

EPE helps contractors and project teams analyse delay, establish entitlement and develop well-supported construction claims.

Continue reading

Related insights

Salini Constructori SpA v. Uganda: How a UGX19.47 Billion Claim on Kampala Northern Bypass Came to Nothing
In the Press
October 5, 2026

Salini Constructori SpA v. Uganda: How a UGX19.47 Billion Claim on Kampala Northern Bypass Came to Nothing

Italian construction company Salini Constructori SpA has lost its attempt to recover about UGX19.47 billion from the Government of Uganda over the construction of the Kampala Northern Bypass, after the High Court found that the amounts claimed had already been paid, determined through arbitration or released under an earlier settlement. Commercial Court Judge dismissed Salini's […]

Read more
When a Contractor Undertakes both the Design and Build of a Project, where does its Liability Begin—and where does it End?
Construction Cases
September 8, 2026

When a Contractor Undertakes both the Design and Build of a Project, where does its Liability Begin—and where does it End?

Case of Fabrication Systems Uganda Limited v Zeus Agro Limited When a contractor undertakes both the design and construction of a project, its responsibilities can extend far beyond simply putting materials together on site. But where exactly does that liability begin? And where does it end? The decision in Fabrication Systems Uganda Limited v Zeus […]

Read more
Meera Investments vs FBW: Lessons for Engineers and Consultants from the Kabira Country Club Case
Construction Cases
August 25, 2026

Meera Investments vs FBW: Lessons for Engineers and Consultants from the Kabira Country Club Case

The dispute between FBW (U) Limited and Meera Investments Limited over the proposed expansion of Kabira Country Club offers an important lesson for Uganda's construction and consulting industry. While the case involves an architectural consultancy, its implications extend to engineers, quantity surveyors, project managers, architects and other professionals involved in major construction projects. At its […]

Read more